A dry, clear-span shed for the tractors, the quad, the loader and a winter's feed and fertiliser, designed and erected by South West Steel Buildings. You get engineered drawings and a price for the building, and a straight answer on the part every frame quote leaves out: the ground it stands on, and the two Welsh consents that come before it.

Usual span
12–18 m
Clear inside. Go longer in 6 m bays before you go wider.
Slab
200 mm
With mesh, for trailers that turn on the same spot every day.
Prior notice
£223
On a holding of 5 ha or more, up to 465 m². The council has 28 days.
Drainage approval
100 m²
Above that, the SAB must approve before you start: £420 on a tight plan, 7 weeks.
Large green clad steel building with a roller door

What you are actually buying

One portal frame, no internal posts, so the loader can run the full length and a trailer can be reversed in and turned without threading between columns. Frames go up at 6 metre centres; you choose the span and the height to the eaves, and you choose them once.

Width is what has to turn inside

A tractor and a trailer with room to walk past needs about 12 metres. Two lines of kit with a walkway between them needs 18. Beyond 20 or so, the extra steel is holding roof up over space you rarely use, and a longer shed is the better buy.

Length is bought in 6 metre bays

Eighteen, twenty-four, thirty. The frames in the middle carry less of the load than the gables, so every bay you add costs less per square metre than the last. If you want more shed, go longer before you go wider.

Eaves height cannot be fixed later

Tipping a trailer, lifting with the telehandler, driving a loaded machine through the door: each wants more headroom than the machine parked. Pick the height for what the farm might run in ten years, not for what it runs today.

What you get asked to decide

  • Open fronts, sliding doors or roller shutters, in the gable or along a side
  • Fibre cement or box profile cladding, with roof lights where daylight helps
  • A lean-to on one side for the smaller kit, cheaper per square metre than the main span
  • Gutters and downpipes, and a clean drain or a tank for the water they carry
  • Supplied for your own people to put up, or supplied and erected

There is one more choice underneath all of those: whether the frame is cold rolled or hot rolled. It changes the price, the lead time, whether you can put it up yourself, and what goes in the ground.

How it goes from here

Five steps, in this order. The fourth is the one nobody prices for you up front, which is why there is a calculator further down this page.

  1. Step 1

    Tell us roughly what you need

    Span, length and what it is for. Approximate is fine — nobody expects you to have decided, and it means the first reply can be useful rather than a list of questions.

  2. Step 2

    Drawings and a price for the frame

    The manufacturer prepares engineered drawings and quotes the building. That includes the pad foundation sizes, which no calculator can work out for you.

  3. Step 3

    Settle the planning position

    Prior approval on a qualifying agricultural holding, or a full application. Worth establishing before steel is ordered rather than after.

  4. Step 4

    Get the base in

    Site strip, level, stone and slab, ready and cured before the erectors arrive. This is the part you can price on this page today.

  5. Step 5

    Delivery and erection

    Delivered for your own team to put up, or supplied and erected. Both are normal; the difference is worth asking about at quote stage, not later.

Get a price for my machinery store

Rough dimensions are enough to start. You get a reply the same day.

Notice or application: the holding decides

In Wales a machinery store on a farm is usually not a planning application. On an agricultural unit of 5 hectares or more, a building of up to 465 m² that the holding reasonably needs goes in as a prior notification: £223, and 28 days for the council to say whether it wants a say in the siting and design. Say nothing and it is approved by silence.

Under 5 hectares the right to put up a new building does not exist, which catches many smallholdings. A store for a contracting business, or for kit that has nothing to do with the land, is a full application on any size of holding. The planning guide works through the size tests, the distances and the fees; the summary below is the short version.

In Wales, farm buildings get their permitted development rights from Part 6 of the 1995 General Permitted Development Order, which splits at 5 hectares — and the two halves are not the same right with different numbers on them.

On a unit of 5 hectares or more, Class A permits a new building, or the extension or alteration of one, if it is reasonably necessary for agriculture on that unit. Its ground area cannot exceed 465 square metres — counted together with anything else put up on the unit within 90 metres in the previous 2 years. It must be no more than 12 metres high and at least 25 metres from a trunk or classified road. England's limits are far larger; they do not apply here.

On a unit of 0.4 to under 5 hectares, Class B does not let you put up a new building at all. It permits a limited extension or alteration of a farm building you already have — no taller, no more than 10 per cent more volume, and no more than 465 square metres in all. With four hectares and nothing to extend, a new shed is a full planning application.

Where Class A applies, you are not applying for planning permission. You notify the council, which has 28 days to decide whether it wants to approve the siting, design and external appearance. You can start when it says it does not, when it approves them, or when 28 days pass without a reply — provided the building genuinely is permitted development in the first place.

One exclusion catches people: no building for livestock, and no slurry or sewage sludge store, within 400 metres of the curtilage of a protected building — broadly, a house that is not part of your own farm.

Two more things are Welsh. Construction of 100 square metres or more needs its drainage approved by the SuDS Approval Body even when it is permitted development. And in a National Park the park authority is the planning authority — here, the Bannau Brycheiniog National Park Authority or the Pembrokeshire Coast National Park Authority.

A summary, not planning advice. The legislation is SI 1995/418, Schedule 2, Part 6 as in force in Wales, checked against legislation.gov.uk on 23 September 2026. The full rules are on our planning guide for farm buildings in Wales. Confirm your own position with the authority that covers your site.

Roof water is a consent, not an afterthought

Welsh Government describes the land as hilly, wet and poor-soiled — its own words are that "Most of Wales is hilly or mountainous and this, combined with relatively poor soil quality and a wet climate, means that much of the land is restricted to the grazing of sheep and cattle." A machinery store roof collects a great deal of that wet, and since 2019 any construction of 100 m² or more in Wales has needed the council's SuDS Approval Body to approve where the water goes before a spade goes in, planning application or not.

For a shed on its own the answer is normally a soakaway sized for the roof, or a tank if you want the water for stock or washing down. The fee is £420 for a site plan of under a tenth of a hectare, the SAB has 7 weeks from a valid application, and if it does not decide in time the application counts as refused, so put it in with the prior notification rather than after it.

The floor, and what arrives on the tyres

A trailer turning under load puts far more through a slab than the same trailer standing still, and it does so in the same two places every day, just inside the door and wherever you always swing round. That is why the preset is 200 mm with mesh over 150 mm of compacted stone rather than the thinner slab a hay barn gets away with. If a loaded grain trailer, a telehandler with a full bucket or a contractor's forager will use it, say so, because the heaviest regular load sets the slab, not the size of the shed.

Give the floor a fall towards the door. Welsh mud comes in on every tyre for much of the year, along with diesel and oil, and a slab that drains to the front is one you can hose; one that puddles in the middle is one you live with.

Sloping fields, and ground that was mined

A level yard is strip, level, stone and pour. A field with half a metre of fall across the footprint is a cut at one end, a fill at the other, and a decision about where the surplus goes. Topsoil usually moves more material than the slope does.

88 m³

Topsoil off a 12 × 20 m platform with 250 mm to strip, before you touch the level. If it leaves the site that is 10 lorry loads, and it is the number nobody budgets.

Dig a trial hole and measure the topsoil instead of guessing from the surface. And in the coalfield councils, from Blaenau Gwent and Torfaen across the valleys to Swansea and Neath Port Talbot, check the mining map before anything is dug: a shed on a shaft or shallow workings needs a specialist's report and sometimes a different foundation, and the map is free where the surprise is not. Each area page says whether that applies where you are.

Grants: an honest no, with one exception to watch

No Welsh Government scheme pays for a machinery store. The open one funds roofs over livestock areas and the equipment scheme funds equipment. The one thing to watch is that SFS Optional: Infrastructure and Equipment, announced and not yet open, lists storage for chemicals, pesticides, fuel or oil among its items. If a bunded fuel or chemical store is part of your plan, keep it as its own line in the design so it can be claimed on its own if the category opens with that item in it. The farm grants guide tracks the status.

The one number no web page can give you

The pads. Each stanchion sits on a concrete base sized by a structural engineer for your span, your eaves, the wind where the shed stands and what your ground will carry. A pad size offered without a design is a guess, and on an exposed Welsh site a bad one. They come with the drawings when you ask for a price. Everything below is geometry from the dimensions you type in.

Work out the base for your machinery store

Preset to a 200 mm slab over 150 mm of stone. A 12 by 20 on level ground is about 52 m³ of concrete to order and 78 tonnes of Type 1; put in your own size and your own field.

Building

Tractors and trailers on and off it daily.

m
m

Slab

Set by the building type above. Change it if you know different.

mm

Each side. Leave at 0 if it finishes flush.

mm

Site

mm

High corner to low corner.

Balanced keeps the dug material on the plot and moves the least.

mm

Dig a trial hole and measure it. This shifts more muck than the slope does.

Concrete to order for the slab
52.0m³waste allowed, rounded to the half metre
Machinery store · slab 246.4 m² at 200 mm · working platform 352.6 m²
Ready-mix plant
Slab concrete
Net 49.3 m³ before waste
52.0m³
Quarry
Type 1 sub-base
Spread 188 mm loose to finish at 150 mm compacted
77.6t
Builders merchant
Mesh sheets
2.4 × 4.8 m sheets, 300 mm laps allowed
28sheets
Damp proof membrane
Laps and upstand included
276m²
Edge detail
Perimeter, for edge insulation or expansion joint
64.8m
Earthworks
Topsoil to strip
110.2 m³ once dug and loose
88.2m³
Cut
17.6m³
Fill
17.6m³

What this does not work out: the pad foundations

The concrete pads the stanchions sit on are sized by a structural engineer, not by a formula. They change with the span, the eaves height, the wind loading on your particular site and what the ground will bear. Anyone quoting you a pad size without a design has guessed it.

Want this priced properly?

Send us the job and we'll get you engineered drawings and a quote for the frame — with the pad sizes this tool can't work out. The figures above go with your enquiry, so you don't have to type them again.

Every enquiry gets a reply the same day, and your figures go with it. The building itself is designed and priced by South West Steel Buildings, our building partner, so your details go to them too, and they will be in touch. How we handle your details.

Common questions

How big a machinery store does a Welsh hill farm need?
Usually smaller than a lowland arable farm and taller than people expect. The kit on a grazing farm is a tractor or two, a quad or a UTV, a loader, a feeder, a topper, a trailer, and a season of fertiliser, feed and fencing materials that all want to be under a roof. A 12 metre span at 18 or 24 metres long covers most of that. The height is the thing to get right: a tipped trailer or a raised telehandler decides the eaves, not the tractor parked on its wheels.
Is a machinery store permitted development in Wales?
On a holding of 5 hectares or more, a new building of up to 465 m² that is reasonably necessary for farming that land is agricultural development: you give the council a prior notification with the £223 fee and it has 28 days to ask to approve the siting and design. Below 5 hectares there is no new-building right at all, and a store for a contracting business, or for kit unrelated to the holding, is not agricultural however it looks. Both cases are a full planning application.
Do I need drainage approval for a machinery store?
If the construction covers 100 m² or more, yes, and a machinery store nearly always does. The SuDS Approval Body at your council has to approve where the roof water goes before work starts, whether or not a planning application was needed. It costs £420 for a shed on a plan of under a tenth of a hectare, the SAB has 7 weeks, and an application not decided in time counts as refused. A soakaway or a rainwater tank designed at the same time as the slab is the usual answer.
Is there a grant for a machinery store in Wales?
Not for the building. The open Welsh Government scheme pays for roofs over livestock feeding, gathering and manure areas, which a machinery store is not. SFS Optional: Infrastructure and Equipment, announced but not open, lists storage for chemicals, pesticides, fuel and oil among its items, and SFS Optional: Capital: Production and Efficiency funds equipment such as water harvesting, not sheds. So plan the store as a cost, and if a bunded fuel or chemical store is part of the same job, keep it separable in case the larger category opens with that item in it.
How much concrete and stone does a 12 m by 20 m store take?
On level ground with a 200 mm slab and a 100 mm oversail, about 52 cubic metres of concrete to order once waste is allowed for, over roughly 78 tonnes of Type 1 compacted to 150 mm. Those two numbers come from the same engine as the calculator below, so change the dimensions there and they move with it.
What is in the frame price and what is not?
In: the steel, purlins and rails, the cladding and roof lights, the doors, and erection if you ask for it. Out: everything the frame stands on. Stripping the site, cutting and filling, the stone, the slab, the drainage and the track in are groundworks, and whether you buy them from the same firm or a local contractor they are a separate bill. A foundation drawing tells you what the slab must be; it never tells you what it will cost, and on a sloping Welsh field that can be a third of the whole job.
What do the prior notification and SAB application cost in Wales?
The prior notification for an agricultural building is £223 from 1 December 2025. It is on the Welsh Government's full cost recovery pathway, so it stays at £223 through 2026 and rises from 1 April 2027: the published policy allows up to 10% or £100 a year, whichever is greater, plus inflation, until the fee covers the council's cost. The SAB application is £350 plus a charge on the construction area shown on your site plan: £70 for every 0.1 hectare or part of one up to half a hectare, less per tenth beyond that, capped at £7,500. A shed on a plan of under 0.1 hectare is £420. If approval is conditional on inspections, each one is £168. The SAB has 7 weeks to decide, 12 with an Environmental Impact Assessment, and an application not decided in time counts as refused.
Do I need planning permission for a farm building in Wales?
It depends first on the size of the holding. On an agricultural unit of 5 hectares or more, Class A of Part 6 of the Town and Country Planning (General Permitted Development) Order 1995 permits a building reasonably necessary for agriculture on that unit, up to 465 square metres — counted together with anything else put up on the unit within 90 metres in the previous 2 years. It must be no more than 12 metres high (3 metres within 3 km of an aerodrome), at least 25 metres from a trunk or classified road, and a livestock building or slurry store must be at least 400 metres from a protected building. Before building you notify the council, which has 28 days to say whether it wants to approve the siting and design. On a unit of 0.4 to under 5 hectares Class B allows only a limited extension or alteration of an existing building, and a new building needs full planning permission; under 0.4 hectares there are no agricultural permitted development rights at all. England's larger limits do not apply in Wales.
Does a farm building in Wales need SAB approval?
If it covers 100 square metres or more and affects how rain soaks into the ground, yes — even when it is permitted development and needs no planning application. Since January 2019 construction of that size in Wales needs approval of its surface water drainage from the SuDS Approval Body, which is run by your local council, before work starts. Farm roofs and clean yards are included, and the rainwater off a new roof is usually the whole question.
Can I convert a farm building to a house in Wales without planning permission?
No. England has a permitted development right, Class Q, that lets some agricultural buildings become homes through a prior approval application. Wales has no equivalent: a barn conversion in Wales needs full planning permission from the local planning authority. Much of what is written about barn conversions online is about England, so check which country it was written for before relying on it.

Get a price for a store the size you will grow into

A rough span and length and what goes in it is enough. South West Steel Buildings designs and prices the building with the pad sizes, and you already have the base costed.