Inside the groundworks calculator
Everything the calculator tells you is one of two things: geometry, which is exact, or an assumption, which is not. Here they are separated, the assumptions are listed with the range they come from, and the maths is shown, so you can check the figures instead of taking them on trust.
The exact part
Areas and volumes are arithmetic on the sizes you enter. The slab is the frame's footprint plus the oversail all round. Its volume is that area multiplied by the thickness, and the stone underneath is the same area multiplied by the rolled depth. No judgement goes into any of it: get the dimensions right and those figures are right.
The cut and fill on a sloping site is exact as well, and it is the sum hardly anyone does by hand.
Cut and fill on a slope
Picture a platform on ground that falls evenly from one side to the other, with the finished level set halfway up so that what is dug from the high side fills the low side. Add up the height of the ground above that level over the whole platform and the result is neat:
cut = fill = area × fall ÷ 8
That is for a balanced platform. Put the level at the bottom of the slope and it is area × fall ÷ 2, all of it cut. Raise the level to the top and it is area × fall ÷ 2, all of it fill.
Take a building 12 by 20 metres on a field with 400 mm of fall and 250 mm of topsoil. Its working platform comes to about 352.6 m². Balanced, the cut is about 17.6 m³. Dug in at the low end, it is about 70.5 m³. Dividing by eight rather than two is why a balanced platform moves so much less earth.
The same example shows why topsoil, not the slope, often decides the muck-away. Stripping that platform takes off about 88.2 m³ before any levelling starts. With the spoil going off site, the balanced platform needs 10 loads and the dug-in one 17.
The assumptions
These are working figures from the trade, not constants of nature. They are sensible defaults and exactly what the calculator uses. Where a range is shown it is genuine, and your supplier or your ground could fall anywhere inside it.
| Assumption | Used | Range in practice | Why it is there |
|---|---|---|---|
| Concrete waste | 5% | Usually 5–10% | Spillage, a formation dug a little deep, and what stays in the drum. The order is rounded up to 0.5 m³ because that is the step plants deliver in. |
| Type 1 density, rolled | 2.1 t/m³ | Often given as 2.0–2.3 | Turns the volume you need into the tonnes a quarry invoices. It depends on the stone the quarry crushes. |
| Type 1, loose to rolled | 1.25 | Trade figure; varies with the roller | How much deeper to spread it than you want it to finish. A 150 mm rolled layer starts at about 190 mm loose. |
| Bulking, topsoil | 1.25 | Wide, by material | Soil that is dug takes up more space than it did in the ground, and the loose volume is what a lorry carries. |
| Bulking, clay | 1.3 | Wide, by material | Wet clay swells more than dry. Much of South Wales has glacial clay near the surface, so treat this as a starting point. |
| Bulking, rock | 1.5 | Wide, by material | Broken rock swells the most. If the dig reaches the sandstone, mudstone or limestone underneath, expect the loads to go up. |
| Lorry load | 12 m³ loose | Depends on the vehicle | An eight-wheel tipper. Where the lane only takes a smaller tipper or a grab lorry, each load is less and there are more of them: ask your haulier. |
| Mesh sheet | 4.8 × 2.4 m | Standard UK sheet | Cover is worked out with a 300 mm lap on two edges, then 5% more for cutting round edges and openings. |
| Membrane allowance | +12% | Rule of thumb | For overlaps between sheets and turning up at the edges. Approximate, but it stops an order for exactly the slab area. |
| Working platform | 1.5 m each side | Varies with the job | Stripped and levelled beyond the slab so there is room for shuttering and machines. It is why the topsoil figure is bigger than people expect. |
What it cannot tell you
Pad sizes. They are designed by a structural engineer from the span, the eaves height, the wind on your site and the bearing capacity of the ground. No formula on a website produces them, and a pad size offered without a design is a guess.
Prices. Concrete, stone and haulage are priced by distance from the plant or quarry, they differ from one end of South Wales to the other, and they move. A price published today would be wrong within months. Quantities are geometry and do not go out of date, so that is what you get. Take them to your own suppliers.
Tonnes of spoil. The calculator counts loads, by volume. Landfills in Wales charge their tax by weight, and how much a load weighs depends on what you dig, so it does not guess at that either. The calculator page explains the tax.
Your ground. Rock at a foot down, old fill where you expected clay, or coal where the map said there might be: any of them changes the figures, and no arithmetic predicts it. A trial hole does.
Why show all this
A calculator that hides its working asks to be trusted instead of checked. You are going to order concrete against these numbers, so you should be able to see where every one of them comes from.
If one of these assumptions is wrong for the way the work is done in your part of Wales, I would rather be told than not. They live in one settings file and can be changed.